2013 Bond Construction Projects Underway at Three CCISD High Schools


Clear Brook, Clear Creek and Clear Lake high schools will all look a little different after bond projects are complete.



The Clear Lake High School rebuild will kick into high gear now, as the City of Houston approved the building permit. The Phase one building pad installation is underway and the foundation layout process will begin over the winter break.  Pier drilling will begin in early January 2015. Phase one should be completed by December 2015 with Phase two in August 2017. Final completion of the rebuild is scheduled for November 2017.   

Additions and renovations planned at Clear Brook High School will begin in the New Year. The building permit needed for the majority of the work has been approved by Harris County. Over the winter break construction will begin on a temporary counselors’ area in a portable building in preparation for a move which will allow the front portion of the current administration area to be demolished. Work on the Career Technical Education and Athletic areas will begin soon as well. Major portions of the work will be completed by December 2015, with the remainder of the work completed by March 2016.

Construction will begin on additions and renovations at Clear Creek High School in April 2015. The design team is working with staff from Clear Creek High School, Athletics, Career and Technical Education (CTE), Fine Arts, Maintenance, Child Nutrition and Technology to develop plans that meet the needs of all students. Once the plans are approved by the CCISD Board of Trustees, construction will begin and the project should be complete by December 2016.

Work is well underway at the CCISD Challenger Columbia Stadium with the home-side retaining walls completed and the roof on the field house scheduled to begin over the winter break.  Structural steel for the press box will be delivered soon and construction is expected to begin in mid-January. Concrete slabs for the home-side restroom buildings, ticket booth and concession stand are also set to be installed in December and January.